We have all seen the “Earned Value Calculation” option in Admin Preferences but how it affects your Earned Value calculations?

user-image
Question added by Aioub Mohamed , Planning and Cost control Manager , Khalid Ali Al-Kharafi & Bros. Co.
Date Posted: 2013/12/11
Aioub Mohamed
by Aioub Mohamed , Planning and Cost control Manager , Khalid Ali Al-Kharafi & Bros. Co.

after too many searching i found a usfel answer  it as 

BAC = BL Budgeted Labour Cost + BL Budgeted Non-Labour Cost + BL Budgeted Material Cost + BL Budgeted Expense Cost.

If the ‘Earned Value Calculation’ is set to ‘At Completion Values with Current Dates’

BAC = BL At Completion Labour Cost + BL At Completion Non-Labour Cost + BL At Completion Material Cost + BL At Completion Expense Cost.

Muhammad Danish Habib
by Muhammad Danish Habib , Cost and Schedule Engineer , Manitoba Hydro

The option of EV calculation let you adjust use of baseline dates and rules of credit 