Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

How can a project manager avoid 'bottle necking' with regards to tasks?

user-image
Question added by Haitham Abu Sharif , Marketing Coordinator , United Electronics
Date Posted: 2013/12/08
Ahamed Shareef
by Ahamed Shareef , Divisional Head - Quality Assurance , Apollo Tyres Ltd

Project planning must be able to identify the bottlenecks in the project so that they can be managed well. CPM will help to identify the bottlenecks in the project - like which portion of the project takes longer lead time or which machine procurement has longer lead time, etc. This may help PM to keep track this bottleneck and ensure all the micro-activities in this area are handled on time.

Francisco Beltran PMP | MBA | MSc Ec.F | CIMA(CGA)
by Francisco Beltran PMP | MBA | MSc Ec.F | CIMA(CGA) , Financial Management Consultant/Modeler , IFSM Consulting

In my opinion the ways of effectively managing bottlenecks include:

1)Process Analysis 2)Determine the capacity of each step in the process3)Process Improvement 4)Measuring process performance 6)Capacity utilization 7)Direct labor content

Raafat Sallam
by Raafat Sallam , Organizational Development and Training Consultant , Training Centers, Marketing Organizations.

By:

1- Good planning

2- Risk analysis

3- Feedback

4- Preventive thinking

amer jayyousi
by amer jayyousi , Business Development Consultant , freelance

Deliver and enhance premium communications,open cultural communication and ensure effortless flow of communication in every direction .

Clodelio Delfino
by Clodelio Delfino , Managing Consultant , Startup Company

Just like with Raafat with minor difference on item#4 since Preventive can be a part of Risk Analysis so I've add Flexibility instead.

 

1. Good Planning

2. Risk Analysis

3. Continous Feedback/Communication.

4. Flexibility to prioritize/deprioritize.

ASIF BE Mech IEng PMP
by ASIF BE Mech IEng PMP , Projects Manager - Buildings Utilities & infrastructure , Qatar General Electricity & Water Corporation

it very straight ..RISK .if you can take risk on your predictive experianced engineers/ managers you can do impossibles so proper budgetting and a safe contract only allow you to do so.

rest is general ya now a days higher weightage is given to mile stone dates and activities so such commercial attraction also work little compromise on quality but many things which can be repeated is acceptable but core engineering and design have no room to play or simply you keep on loosing quality and reliability of your work ,project and hence company

Harendra Nishshanka
by Harendra Nishshanka , Network Consultant , Mannai Trading Co WLL

Deviding a task to small pieces and assign it to individuals to reduce the risks.

Add a deadline to small task pieces.

 

Mohammad Tohamy Hussein Hussein
by Mohammad Tohamy Hussein Hussein , Chief Executive Officer & ERP Architect , Egyptian Software Group

By using a project management system which they are trained to use. If they do that they will discover the issue at the planning phase and resolve it befor baselining the project. If thi happens during the project's execution, they can still use the system to resolve the issue (some systems allow for what-if analysis). Resolusion of such issues during execution usually results in imapcting the time an/or the cost of the project unless adequate risk mitigation considerations were built into the project plan.

Suleman Hasib
by Suleman Hasib , System Administration Manager , Freelancer

First Identify the Constraints. Generally following three are considered as major:

1. Human Resource

2. Budget

3. Processes

 

1. For Human Resource avoid conflicts between team, Describe Job descriptions clearly. Promote team building go out with your team on any event to reduce differences and make the team a family.

 

2. For Budgets first of all carefully consider every aspect and forsee future contigencies.

And most of the times shortfalls in budgets are due to ineffective managemnt of resources. Try to reduce the wastage for everything even for minor things.

 

3. For Processes use software tools to track activities. Dependent activities need more attention to their input from another activity cause dealy in such activity will result in chain delay.

Use Software tools like MS Office Project and Primavera etc.

Gantt Charts will play important role in activity tracking.

Perform variance analysis regularly for Timelines, Costs and Quality.

 

Above all appreciate and motivate your team. 

 

Hope it helps.

 

 

 

Jasmin Mathai
by Jasmin Mathai , Executive / Administrative Assistant to Assistant Vice President , United Arab Shipping Co.

If all tasks are well planned, scheduled and delegated / assigned to the right persons working under you, then you can avoid bottle necks and oversights.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.