What is the checklist points prior to pouring concrete of slab/ columns?

user-image
Question added by Sahariman Kabir , Civil Project Engineer , Al Rostamani Pegel
Date Posted: 2021/12/04
muhammad Zeeshan
by muhammad Zeeshan , Site Engineer , Desert Wave Construction Co. Ltd

 

Conduct a pre-slab meeting to iron out plans.

Inspect formwork thoroughly. ...

Check reinforcing steel. ...

Make sure you have the right materials and equipment. ...

 

Double-check the materials and job site to ensure readiness