Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

How Can we add column in Primavera P6 showing Percentage Weightage for each activity and WBS for the Budgeted Total Cost?

user-image
Question added by Mudassir Hussain , Project Planning Engineer , M.A Kharafi and Son
Date Posted: 2020/09/22
RIYAZ ABUBAKAR
by RIYAZ ABUBAKAR , Lead Planning & Scheduling Engineer , Al-Muzain

Go to column and select

Budgeted labor cost + Budgeted non labor cost then make it sum  

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.