Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which of the following statements regarding WBS are FALSE?

A. The WBS is used to show which work components have been assigned to which organizational units. B. Each item in the WBS is generally assigned a unique identifier that can provide a means to track costs and resources C. The WBS is an output of the Create WBS process D. The WBS is deliverable-oriented grouping of project components that define the total scope of project

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/06/19
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. The WBS is used to show which work components have been assigned to which organizational units. 

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.