Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are in the process of developing an approximation of the costs of the resources needed to complete each schedule activity.?

All of the following are tools/ techniques you can use in this process EXCEPT: A. Analogous estimation, bottom-up estimation, parametric estimation B. Vendor bid analysis, reserve analysis C. Cost of quality, project management software D. Determine resource cost rate E. Cost aggregation

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/05/08
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. Cost aggregation -------------------

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.