You are in the process of monitoring the various project processes and their performance. Which of the following?

is the LEAST appropriate output of this process? A. Requested changes B. Recommended corrective actions C. Recommended defect repair D. Recommended preventive actions E. Project scope statement updates

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/03/06
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. Project scope statement updates