Which of the following is the total amount of time that a scheduled activity may be delayed from its early start date without ?

delaying the project finish date? A. Critical float B. None of the choices are correct C. Average float D. Total float E. Free float

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/02/14
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Total float ------------------------