Contract documentation is an input to the Contract Closure process. What does the process consist of?

A. Approved change requests B. Supporting schedule C. Procurement audit documentation D. Warranties E. Payment records

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/01/02
MURAT MIDIK
by MURAT MIDIK , SAP Project Manager , Spectrum Consulting

Correct Answer is C.: Procurement audit documentation

احمد صالح عبد الفتاح علي اسماعيل
by احمد صالح عبد الفتاح علي اسماعيل , Associate Professor , Helwan University

E. Payment records

The buyer must have accepted the deliverables and agreed that they were delivered as promised withinthe contract. Also, the buyer must have completed the financial obligations on his end. All payments, including any finalpost-deliverable payment, must have been received by the seller, before a contract can officially be considered closed.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Procurement audit documentation