Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

A project manager reported the following Earned value data: PV: $12,400,000, EV: $14,500,000, AC: $14,500,000 ?

What does this mean? A. The project is under budget and on schedule. B. The project is on budget, but behind schedule. C. The project is on budget and ahead of schedule. D. The project is over budget and on schedule.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/10/03
Abhijit Bera
by Abhijit Bera , Assistant Manager Planning , Tata Projects Ltd

Form the data provided PV = $12,400,000, EV = $14,500,000 & AC = $ 14,500,000

It can be understood that,

1) AC > PV (i.e project is over budget on the specified Data Date)

2) EV > PV (i.e. project is ahead of schedule on the specified Data Date)

so the answer should be "The project is over budget & ahead of schedule" .

As this is not an option, so option (c) can be considered only if AC=BAC on the specified data date.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. The project is on budget and ahead of schedule.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.