Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

How much does primavera contribute in your Progress measurement system (Out of 10)?

user-image
Question added by Zabiulla Shakir Ansar Ismail , Planning Engineer , TRADING & AGENCY SERVICES (TRAGS)
Date Posted: 2018/09/27
Abhijit Bera
by Abhijit Bera , Assistant Manager Planning , Tata Projects Ltd

Primavera is a detailed project scheduling and monitoring tool, with its capabilities limited only to the level of detail that you incorporate in your schedule. For progress measurement primavera can be rated between (6 to 10) based on the details that you are incorporating in it, i.e. activities loaded and update for resources, physical progress, costs & remaining forecasted durations. The factors that can influence the choice of primavera base progress measurement system would be,

1. The No. of activities to be updated

2. The frequency of update (i.e. daily, weekly, fortnightly, monthly, Quarterly)

3. The amount of detail to be updated

For large projects it is practical to use a combination of Excel & Primavera to develop your project measurement system.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.