You are a project manager for a software project. As you are defining the scope of the work you need to do, you sit down with ?

all of the project's stakeholders and record all of the requirements you can get from them. Which of the following is NOT a valid requirement from stakeholder analysis? A. The quality of the product must t within organizational metrics for software quality. B. The budget must be within% of our projected cost. C. The work the team does must be better than they did on their last project. D. There can be no more than5% schedule variance on the project

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/09/16
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: CExplanation: Saying that the work must be "better" is subjective. Requirements gathered in stakeholder analysis need to be quantifiable. That way, the team has a goal they can shoot for and you can always tell how close or far from it you are.