Your company's quality assurance department has performed a quality audit on your project. They have found that your team has?

implemented something inefficiently, and that could lead to defects. What's the NEXT thing that should happen on your project? A. You document recommended corrective actions and submit them to the change control board B. You meet with the manager of the quality assurance department to figure out the root cause of the problem C. You add the results of the audit to the lessons learned D. You work with the quality department to implement a change to the way your team does their work

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/08/08

In my business, the process of quality control inspection is difficult for me. So I decided that it was time to look for an assistant. I found a great app https://fluix.io/quality-inspection-workflow which helped me automate the quality control process. Now I can do other things while the application is working on a complex process.

Jyothsna Vidavaluru
by Jyothsna Vidavaluru , Project Manager, Scrum Master, Agile Coach , Larsen & Toubro Infotech Limited

Immediate action has to be option A, then B, C follows. Option D is not acceptable, since we can never compromize on quality.

Jomar Depone
by Jomar Depone , Admin Technical Executive , HTC Technical and Cleaning Services

The next thing is to document recommended corrective actions and submit them to the CCB. The board will evaluate and judge wether the change is acceptable.

Stephen Onyia
by Stephen Onyia , Mechanical Engineer Rotary & Static Equipment. , Saipem - Nigeria

D:You work with the quality department to implement a change to the way your team does their work.

 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: AExplanation: Quality Audits are when your company reviews your project to see if you are following its processes. The point is to figure out if there are ways to help you be more effective by finding the stuff you are doing on your project that is inefficient or that causes defects. When you find those problem areas, you recommend corrective actions to fix them.

For me, networking is very important, because it helps to build a network of contacts that allows you to quickly and effectively solve life problems and business issues.

Our response shall be proceeded in below order:

B

A

C

D

AHTSHAM ZAHEER
by AHTSHAM ZAHEER , Sr. Manager , Zahid Jameel & Co., Chartered Accountnats

B followed by A, then D and finally C.