Which of the following is NOT typically found in a project charter?

A. Project requirements B. Authorization for a project manager to work on a project C. Work packages decomposed into activities D. An initial set of schedule milestones

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/08/08
Jomar Depone
by Jomar Depone , Admin Technical Executive , HTC Technical and Cleaning Services

Work packages decomposed into activities is not typically found in a project charter since project have not been started.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: CExplanation: The project charter is created long before you start identifying work packages and activities. Those things are done as part of the project planning, which only happens after the project charter is completed.