Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which of the following is NOT an example of a deliverable?

A. Parametric Estimation B. Work Breakdown Structure C. Project Schedule D. Project Management Plan

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/06/27
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: AExplanation: Parametric estimation is a tool for creating estimates. It's not a deliverable.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.