Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What is the BEST way to make an accurate forecasting of ETC? Manual Forecasting of cost of remaining work. BAC – EV (BAC – EV)/CPI EAC - AC

user-image
Question added by Zakir Muhammed , Contract Administrator , DS Contracting Co.
Date Posted: 2018/06/23
Mohammed Qaisar I PMP I MCIPS I MBA
by Mohammed Qaisar I PMP I MCIPS I MBA , Group Procurement Manager (Civil) , Al Ghurair Construction LLC

As per PMBOK6, it is the manual forecasting of the cost of remaining work.

Zakir Muhammed
by Zakir Muhammed , Contract Administrator , DS Contracting Co.

Manual Forecasting of cost of remaining work.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.