Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

How to solve the problem of Inability of electrical grid on enduring the renewable energy projects?

user-image
Question added by Zaid Alshufiyyen , Head of Energy Sector Section , Energy & Minerals Regulatory Commission
Date Posted: 2018/04/18

Try with power factor correction!

ersen akdeniz
by ersen akdeniz , Chief Electrical Engineer , Borusan ENBW Energy Investments

if the point of common coupling is weak in terms of SC-MVA capacity, further transmission system investment is required for safe/reliable/stable operation

Diversity and wide geografical distribution of renewable sources can be a solution.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.