The process to change a contract clause is _ the project change control system.?

 A. Integrated within. B. Unrelated to. C. The same as. D. An input to. E. None of the above.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/03/21
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. Integrated within. ------------