Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

The authority to accept or reject a requested change in a large and complex project, should rest with _?

 A. The sponsor.B. The president. C. The change control board. D. The client. E. The project manager.

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/03/21
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. The change control board. ------

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.