Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which of the following concepts refers to a response to a risk event that was not defined in advance and is currently happening?

A. Risk mitigation response. B. Incidence response. C. Workaround response. D. Corrective action response. E. Contingency response.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/03/14
Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the correct choice.

Asheen Prem
by Asheen Prem , AutoCAD Electrical Draughtsman , COMMANDtech CAD & IT PVT LTD

Option C) WORKAROUND RESPONSE

Because, Workarounds are responses to any unidentified risks that occur during the project execution. 

يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation 

I agee the option C

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Workaround response.  ------------------

Muhammad Zeeshan
by Muhammad Zeeshan , Intrainee in Tax and Audit Department , BMC ( Business Management Consultant)

The Answer is Contingency response

Mousa   Elsheikh FLMI
by Mousa Elsheikh FLMI , Business Consultant , Aljazira Takaful

B , just like the fall of crane two years ago in Makkah , the fall was not defined and a risk , therfore no contngency or mitigation were defined . every body had to deal with it as an incidence 

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.