When performing scope control, which of the following options is necessary?

A. A charter update. B. Risk mitigation. C. Scope verification. D. The cost-benefit analysis.

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/03/07
Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the correct choice.

Yaqoub Alomar
by Yaqoub Alomar , Civil Engineer , Al-Zubeir municipality

C. Scope verification.

_______________________

_______________________

 

C. Scope verification. Multi disciplinary teams must meet to finalise and "box up" the scope. Being 100% sure of what is required will reduce the chance of scope creep. 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

nswer: CExplanation: Project scope control is concerned with influencing the factors that create project scope changes and controlling the impact of those changes. Scope control assures all requested changes and recommended corrective actions are processed through the project Integrated Change Control process. Project scope control is also used to manage the actual changes when they occur and is integrated with the other control processes. Uncontrolled changes are often referred to as project scope creep. Change is inevitable, thereby mandating some type of change control process