Which of the following represents the final task during project close-out?

 A. Reassignment of team member. B. Verification that contractual obligations were met. C. Transferring the deliverables to the client. D. Completion of performance/lessons-learned records.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/02/14
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Transferring the deliverables to the client.