Which of the following represents a consequence to the project in the event of a resource being added to the project team during execution?

A. Shorter project completion schedule. B. An indeterminable effect. C. A requirement for a scope change. D. An increase in project quality.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/02/08
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. An indeterminable effect.