Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

The document that authorizes the release of organizational resources to the project is the _?

A. Charter

B. Statement of Work

C. Project Design Plan

D. WBS

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/11/23
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: A

Explanation: The Charter (contract) is the document that formalizes the project.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.