Resource Leveling is a technique for?

A. Estimate Activity Duration

B. Estimate Activity Resources

C. Develop Schedule

D. Sequence Activities

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/10/13
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation: Resource Levelling Heuristics: Allocate scare resources to critical path activities first etc. Tools and Techniques for Develop Schedule are: Mathematical analysis, Duration compression, Simulation,Resource -leveling ,Project management software, Adjusting Leads and Lags and Coding structure.