A. The highest uncertainty is at this stage of the project.
B. The cost associated at the initial phase of the project is highest.
C. All of the other alternatives apply
D. Stake holders have maximum influence during this phase
Answer: B
Explanation:
minimum cost at the project initiation stage because minimum requirement of resources .