Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery store chain. You have?

your activity list in hand and are ready to diagram the activity dependencies using the PDM technique. Which of the following statements is true?

A. PDM is also the AOA diagramming method.

B. PDM is also the AON diagramming method.

C. PDM is also the AND diagramming method.

D. PDM is also the ADM diagramming method

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/09/30
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

Explanation:

The precedence diagramming method is also known as the activity on node (AON) diagramming method.

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.