Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which of the following processes allow an unsuccessful bidder to seek remedy for contract award to another bidder?

A. award Protest

B. any of the above processes can be used

C. bid protest

D. bid review

E. award review

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/09/23
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C -------------------------

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.