The project is design & build there was discrepancy between the actual status & geotechnical report, shall the contractor claim or do it on his cost?

user-image
Question added by Basem Karam , Project Manager , Consolidated engineering ( Khatib & Alami )
Date Posted: 2017/09/20
Ahmed El-Orabi
by Ahmed El-Orabi , Geotechnical Design Manager , Menard vibro Middle East

it depends on who executes the site investigation campagin and if it is under the contractor laibility ! 

if it is not under the contractor laibility, then he shall claim.

Mohammed Balla Khartoum Sokker
by Mohammed Balla Khartoum Sokker , Senior Engineering Geologist , Dams Implementation Unit

the Contractor shall claim

Manuel Azancot
by Manuel Azancot , GEOTECHNICAL PROJECT COORDINATOR , AMUNDARAY INGENIERÍA GEOTÉCNICA, C.A.

The contractor shall do it on his cost, because the geotechnical report shows the characteristic of soils and rocks of the construction´s site before the construction work. The Geotechnical report is the fundamental data for the foundations design, if there was discrepancy is for change on the design work or construction work.

Temitope Adelabu
by Temitope Adelabu , Civil Engineer , Dabito Construction and Design Ltd

The contractor can't make claim for the additional cost incurred in the process of reworking the foundation design because its a design and build project. The contractor should have engaged a  competent geotechnical specialist to ensure a detailed and accurate geotechnical investigation was carried out.