A. Management Overheads
B. Activity Cost Contingency Reserve
C. Project Management Planing
D. Management Contingency Reserve
Answer: D
Explanation: The difference between the Cost Baseline and Funding requirement at Project completion is Management Contingency Reserve. Management Contingency Reserve is not part of project cost baseline.