You are project manager for a project. This project was originally scheduled for completion in 1 year but already 2 years over and now also project?

 is in execution phase. Which statement is TRUE about the project? 

A. requirement added later therefore project is running late

B. temporary project

C. key resource has left the organization therefore running late

D. limited license of development environment therefore running late

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/08/04
Mohammed Qutubuddin Irfan
by Mohammed Qutubuddin Irfan , Facility Coordinator , SNC LAVALIN ARABIA

According to me Answer is A, as other options can be managed and achieved, whereas if additional scope is added to the actual contract and amendment contract is signed then need to revise the implementation plan and execution so it will change project completion date.

 

Bhavna Thakkar
by Bhavna Thakkar , Assistant Manager Supply Chain & Logistics , Poneer Gulf FZE (Pioneer Electronics)

limited license of development environment therefore running late

Basim Jaffer Dawood AL-Abdwani
by Basim Jaffer Dawood AL-Abdwani , Business Development Executive , Al-Farqadain Tourists& Travels LLC, Doha, Qatar

Training/Development impact on the employees' performance.

Kapila Kumara Ediriweera
by Kapila Kumara Ediriweera , PROJECT MANAGEMENT , INDP Consultancy

I would select answer A.

In my opinion all of the other answers are not quite suited to answer by the Project Manager. Specially answer C is not suited at all as resource management or resource allocation is PM's responsibility and this matter wouldn't be a major issue for extending the project by another year. However, if the issue was an unavoidable, then all stakeholders should approve the extension.

Keith Gregory Wright
by Keith Gregory Wright , Program Director , DynCorp International

If your project is 2 year late in 1 year project some one has a serious problem. Time is money somebody has to pay. 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

Explanation: Project is continuing to expand means it is temporary project.

Other options can be achievable to complete the project if it is important for organization.

C.key resource has left the organization therefore running late