Submitting more applications increases your chances of landing a job.

Here’s how busy the average job seeker was last month:

Opportunities viewed

Applications submitted

Keep exploring and applying to maximize your chances!

Looking for employers with a proven track record of hiring women?

Click here to explore opportunities now!
We Value Your Feedback

You are invited to participate in a survey designed to help researchers understand how best to match workers to the types of jobs they are searching for

Would You Be Likely to Participate?

If selected, we will contact you via email with further instructions and details about your participation.

You will receive a $7 payout for answering the survey.


Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You have been assigned to a project in which the objectives are to expand three miles of the north-to-south highway through your city by two?

lanes in each direction. You are interested in implementing a new project process called Design-Build in order to speed up the project schedule. The idea is that the construction team will work on the first mile of the highway reconstruction at the same time the design team is coming up with plans for the third mile of the reconstruction rather than completing all design before any construction begins. This is an example of

A. fast tracking

B. managing the projects as a program

C. co-location

D. progressive elaboration

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/07/22
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. fast tracking ------------------