Comparing target dates with the actual or forecast start and finish dates is called?

A. Variance Analysis B. Earned Value C. Progress Reporting D. Crashing

user-image
Question added by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
Date Posted: 2017/06/22
Sherif Shabaan
by Sherif Shabaan , Road works project manager , Med Block Contracting and Engineering Consultancy

The comparison of the target dates and the actual are important things to see on the extent of the supposed accomplishment

Babrak kirmal
by Babrak kirmal , Lead Planning Engineer , Sepco Power China

VARIANCE ANALYSIS IS WE USED TO COMPARE THE TARGET DATE WITH ACTUAL DATE OR FORECAST DATE.

As per my understanding that A. Variance Analysis is the best answer

ZULFIQAR ALI
by ZULFIQAR ALI , Project Controls Manager , Nakheel Dubai

Variance Analysis is correct answer.

A. Variance Analysis

 

Zulfiqar Ali Abro
by Zulfiqar Ali Abro , Lead Planner/ Scheduler , SNC Lavalin, Calgary Alber

I fully agree with frineds.

Correct answer is A. Variance Analsysi

Sunit Kumar
by Sunit Kumar , Admin Coordinator , CAMERON GROUP OF SCHLUMBERGER

Always follow (FIFO) first in and first out