You are a project manager for Dutch Harbor Consulting. Your latest project involves the upgrade of an organization's operating system on 236 servers?

You performed this project under contract. You are in the Contract Closure process and have reviewed the contracting process to identify lessons learned. What is the name of the tool and technique you used to perform this function?

A. Performance audits

B. Performance reviews

C. Procurement audits

D. Procurement reviews

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/06/11
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Procurement audits -----------------------

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Answer is C - Procurement Audits where procurement contract & processes are reviewed normally by procurement & project manager before closing the procurement / contract and thanks for the invite.  