Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

During development of schedule in Primavera P6, what will you prefer to develop schedule though the WBS or Coding?

user-image
Question added by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
Date Posted: 2017/06/05
Devi Prasad Mishra
by Devi Prasad Mishra , Project Controls Manager , Black & Veatch Private Limited

WBS is rigid in hierarchy and preferably the schedule should be developed based on using WBS- WBS is developed based on scope.

Activity codes comes in handy when- we have to run reports, filters,sort, organising for further analysis and reporting.

Activity codes provide greater flexibility for review and analysis than the WBS and activity codes can be used for multiples projects once created.

ZULFIQAR ALI
by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

I fully agree with friends that WBS is perfered as compared to activity coding in Primavera. Activity coding help to organize the project as required

ZULFIQAR ALI
by ZULFIQAR ALI , Project Controls Manager , Nakheel Dubai

In Primavera P6, mostly all planners work on WBS. In P3 it was Activity coding

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.