During development of schedule in Primavera P6, what will you prefer to develop the schedule through, the WBS or Coding?

user-image
Question added by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
Date Posted: 2017/06/05
ZULFIQAR ALI
by ZULFIQAR ALI , Project Controls Manager , Nakheel Dubai

WBS is more used now a days as compared to activity coditing strucutre.

Ahmed Mohamed Abdel Kader Al-Assar
by Ahmed Mohamed Abdel Kader Al-Assar , Project Control Engineer , QU

Work breakdown structure is more detailed to organize the scope of works and its needs

I will prefer WBS while development of schedule in P6. Activity coding can be used for organizing the schedule.

Earlier using P3 it was very difficult to use WBS and if you wanted to make changes it was a disaster. But now in P6 WBS is more easy and flexible. The best way to go in P6 is WBS, in my opinion.

Binil Paul
by Binil Paul , Senior Planning Engineer , Keo International Consultants - Qatar

WBS is the easiest to build 

but if you combine it with Activity codes , then your schedule is more powerful in reporting 

hence a combination is the best option