If RFI (request for information) is approved, but change order is not approved. What can be the reason?

user-image
Question added by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
Date Posted: 2017/06/01
RAYSON MENDOZA
by RAYSON MENDOZA , Sales Operations Coordinator; Executive Secretary; Document Controller; Training Facilitator , Unibeton Ready Mix

Reason could be cost, the cost for the change order might be too high and would entirely affect the project schedule.

Atif Muhammad
by Atif Muhammad , Senior Planning & Project Control Engineer , Hastie Saudi Arabia LLC ( Sharqawi CO)

Cost or time required to implement change will exceed project schedule.

AHMER MUSLIM
by AHMER MUSLIM , Inventory Management , Lucky Motor Corporation Ltd

Sometimes change order gives rise to entirely new sub-project with-in that project, which certainly not falls into the viability of the organization. Another reason could be that change order tends to alter the original contract, which requires much more time and cost.

Arun Kumar Kulshrestha
by Arun Kumar Kulshrestha , Senior Project Engineer , Dodsal E&C Pte. Ltd.

RFI approval does not necessarily mean approval of change in scope and/or schedule impact. In case RFI has been issued and approved for clarification on technical matters without impacting project specs etc. then change order may not be entertainted by the client.

I have faced above situations in one of my projects. Please revert incase some for clarification is required.

Skanda Kumar
by Skanda Kumar , Associate Manager , Excelsoft Technologies Pvt Ltd

RFI is only a request for information, there could be multiple reasons for a culminated change order to be rejected, cost, production schedule could be one of them. An approved and completed RFI will not automatically provide an approval for a change order.

Razi Ullah
by Razi Ullah , Senior Cost Engineer , Peace River Hydro Partners

RFI does not change value of PO or contract, it is just a request to the vendor for information. Even if it is approved, the change order may not necessarly be approved. The change order maybe rejected for reasons like cost, schedule, new technology, no expertise etc.