Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

It is useful to conduct project risk assessment according to the project's?

A. network

B. Work Breakdown structure

C. statement of work

D. charter

E. budget

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/05/18
hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Agreed with Option B

With greetings and appreciation

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. My answer is B

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Out of the given, my first preference is option D - Charter ( Project Charter which tells us about the high level risks and risks based on what is and what is not included in the project ) . whereas WBS is used in identifying potential risks at both Micro & Macro level.

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option B is the correct choice.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.