Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the?

A. program and evaluation review technique

B. cost/schedule control system

C. Work breakdown structure

D. milestone review and schedule technique

E. planning programming budget system

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/04/28
Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

It is more convenient answer is Option C .

C. Work breakdown structure

is the correct answer 

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C - Work Breakdown Structure

Matthew Chukwumah  Ajuwa
by Matthew Chukwumah Ajuwa , Safety coordinator and Logistics , ALCON NIGERIA LTD(CONSTRUCTION) SHELL CONTRACTOR

Program and review techniques (option A)

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion -  C. Work breakdown structure

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Out of the given , option C - W B S is most appropriate choice.

Muhammad Alam khan
by Muhammad Alam khan , Director General , Government of Pakistan (various ministries, divisions, departments, corporations)

B is the only possible answer.

muhammad waqas yasir
by muhammad waqas yasir , Chief Executive Officer , SAHAR 3G Kabul, Afghanistan

c is the appropriate answer. WBS is the way but if it has the combination of PERT than we will have better analysis

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.