What are the required supporting documents for submitting interim payment application?

user-image
Question added by Jensil Khan MB Ahamed , MEP Quantity Surveyor / Procurement Quantity Surveyor , Atham Bawa & Sons
Date Posted: 2017/03/13
James Ronhele Galman
by James Ronhele Galman , Quantity Surveying , ARABTEC TAV Joint Venture

Measurement sheets with approved drawings, inspection reports/survey reports, BOQ summaries, Materials on Site, bonds/insurance and the summary

Sulaima lebbe Musakkeer
by Sulaima lebbe Musakkeer , Quantity Surveyor , Singapore Engineering & Contracting WLL

Approved Drawing, Marked Drawing, BOQ Summary with Measurement Sheets, WIR, MIR (Material on site) with material delivery notes with bills and Bonds & Insurances

Jabran Ashraf
by Jabran Ashraf , Quantity Surveyor , China Xinjiang Beixin Construction & Engineering (Group) Co.

B.B.S , Steel Test Report, Concrete Test Report, General Items Details Etc

Waqas Ahmed
by Waqas Ahmed , Quantity Surveyor , Habib Rafiq (Pvt) Limited.

Measurement sheet, Abstract cost and Summary