Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are working on a project that requires resources with expertise in the areas of hospitality management and entertainment. You are preparing your?

 

 project schedule network diagram and know that you will use only finish-to-start dependencies. Which of the following diagramming methods does this describe?

A. Network template

B. PDM

C. AON

D. ADM

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/03/03
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion the correct option is D

Explanation:

The arrow diagramming method uses only finish-to-start dependencies.

Anish Ali
by Anish Ali , Head Projects , LM Energy & Software Pvt Ltd

Its option B i.e. PDM (Precedence Diagram Method) which is used for scheduling activities in a project plan. It’s a method of making project schedule diagram using nodes to represent activities and connect them with arrows.

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. My answer is option D-The arrow diagramming method.

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

 

Option D

 

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I will go with B - PDM and PDM is also referred as AON.

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. Sorry, I don't know about it.

Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

The correct answer is Option D - ADM.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.