Submitting more applications increases your chances of landing a job.
Here’s how busy the average job seeker was last month:
Opportunities viewed
Applications submitted
Keep exploring and applying to maximize your chances!
Looking for employers with a proven track record of hiring women?
Click here to explore opportunities now!You are invited to participate in a survey designed to help researchers understand how best to match workers to the types of jobs they are searching for
Would You Be Likely to Participate?
If selected, we will contact you via email with further instructions and details about your participation.
You will receive a $7 payout for answering the survey.
Register now or log in to join your professional community.
project schedule network diagram and know that you will use only finish-to-start dependencies. Which of the following diagramming methods does this describe?
A. Network template
B. PDM
C. AON
D. ADM
In my opinion the correct option is D
Explanation:
The arrow diagramming method uses only finish-to-start dependencies.
Its option B i.e. PDM (Precedence Diagram Method) which is used for scheduling activities in a project plan. It’s a method of making project schedule diagram using nodes to represent activities and connect them with arrows.
Thank you for invitation. My answer is option D-The arrow diagramming method.
Thank you for the invitation
Option D
I will go with B - PDM and PDM is also referred as AON.
Thank you for the invitation. Sorry, I don't know about it.
The correct answer is Option D - ADM.
My answer is for option (B) PDM