Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or?

additional resources should be assigned to:

A. All activities.

B. Those activities with the greatest degree of risk.

C. Those activities on the critical path beginning with the longest time duration activities.

D. Only those activities with the longest time durations.

E. None of the other alternatives apply

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/02/17
hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Option C 

 

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. I would like to choose option C as my answer.

Muhammad Umar Farooq
by Muhammad Umar Farooq , IT Program Leader , Petro Rabigh

Actually Both B and C are correct. Critical Path activities have the greatest risk.

 

I shall choose C, because it is in detail that B.

 

To get more information on Project Management, follow the following page:

https://www.facebook.com/ProjectLife-1112296792185437

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion - C. Those activities on the critical path beginning with the longest time duration activities.

My answer is for option B. Those activities with the greatest degree of risk.

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I seem C option appropriate.

subrahmanyam gorthi
by subrahmanyam gorthi , Deputy General Manager Legal , Suzlon Energy Limited

It depends. Few of the activities may require additional resources to be deployed while few of them requires stretched targets. Either the case, the management decision shall be given with utmost priority and ensure no penalty payments become due or payable. 

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.