Register now or log in to join your professional community.
A. None of the other alternatives apply.
B. Leveling.
C. Quantification
D. Partitioning
E. Allocation.
It is B - Leveling ; after all resource smoothing is a modified form of resource leveling .
Thank you. May be option B is good answer.
The correct answer is Option B.
My answer is for option (B) Leveling