The first step in WBS creation is?

 

 

A) Determine cost and duration of each project deliverable

B) Identify major deliverables of the project

C) Identify components of each deliverable of the project

D) Determine the key tasks to be performed

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/11/26
ZULFIQAR ALI
by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

There are 3 simple steps to create a work Breakdown Structure 

  • Start with the high level tasks or deliverables
  • Identify subtasks
  • Describe each taskMy answer is B as per your question.

B) Identify major deliverables of the project

Md Fazlur Rahman
by Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

Option D: ..........................................................