Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which of the following statements are TRUE regarding various Activity Scheduling tools?

A. PDM allows for conditional branching and iteration of activitiesB. PDM uses activity-on-node (AON) diagramming method.C. PDM allows for conditional branching and iteration of activitiesD. PDM uses analogous methods as an estimation technique

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/09/25

Option (B) PDM uses activity-on-node (AON) diagramming method

Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-B, PDM uses activity-on-node (AON) diagramming method

 

PDM = Precedence diagram method

 

Nader Ali
by Nader Ali , Technical office manager , AlSafwa Contracting

My Answer is B uses AON method

Thanks for invitation -

With the choice - B *

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.