Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You’re looking for a seller to do work for your project. When do you send out an RFP?

 

A. After you create the procurement documents, but before you select the seller

B. Before you plan contracting, but after you Plan Procurements

C. After the bidder conference, but before you select the seller

D. During Administer Procurements

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/09/04
Rania Garas
by Rania Garas , Contracts Manager , Schlumberger Overseas SA

During the tendering phase

Ahmad Sabry Ismail PMP - RMP
by Ahmad Sabry Ismail PMP - RMP , Construction Project Manager , ICAD

 During Administer Procurements

Ghulam Farid
by Ghulam Farid , Contracts Officer , Abu Dhabi Company for Onshore Petroleum Operations (ADCO)

Option B seems ok.........

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.