The scope baseline consists of what?

A) Scope statement, WBS, and WBS dictionary B) Cost baseline, quality baseline and schedule baseline C) Configuration management plan and configuration identification   document D) Procurement statement of work and project scope statement

user-image
Question added by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
Date Posted: 2016/08/15
Yahya Bah
by Yahya Bah , Principal & Marketing Consultant , International Community

The scope baseline consits of WBS, WBS dictionary and the Scope statement.

Mohammad Abo Al-Afiya
by Mohammad Abo Al-Afiya , Technical Engineer in Project Management Department , Art Bright

The scope baseline consists of:

Choice number (1)

Riad Boughannam
by Riad Boughannam , Civil Engineer , Self Employed

The scope baseline includes : Scope statement,WBS and the WBS dictionary

Tareq Elfurjani
by Tareq Elfurjani , construction engineer , Privet Sector

Thanks for invitation :

scope statement

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A) Scope statement, WBS, and WBS dictionary

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.