Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

In PERT analysis, the time estimates of activities and probability of their occurrence follow?

(A) Normal distribution curve

(B) Poisson's distribution curve

(C) Beta distribution curve

(D) None of the above

user-image
Question added by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
Date Posted: 2016/08/08
Mohamed Hamed
by Mohamed Hamed , Continuous Improvement Specialist (Black Belt) , Woodward Inc

C) Beta distribution curve

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.