Which of the following is NOT an input of the Contract Administration process?

 

A. Selected Sellers

B. Contract Management Plan

C. Procurement Management Plan

D. Work Performance Information

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/07/29
Nader Ali
by Nader Ali , Technical office manager , AlSafwa Contracting

The answer is C) Procurement Management Plan

Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

B. Contract Management Plan